Applied Digital Reaches Ready for Service for Building 2 Phase 1 at Polaris Forge 1
2nd article in the last 90 days, one of 19 articles referencing Applied Digital. Previous coverage: Applied Digital Reaches Significant Milestone, Surpassing 1 GW of Contracted Capacity with U.S. Based High Investment-Grade Hyperscaler Lease at Fourth Campus, Polaris Forge 3 (May 2026).
Companies mentioned
Best suited for
- Seniority
- EVP / SVP / VP / AVP
- Job function
- Chief Operating Officer
- Persona
- Platform / Infrastructure Operations Leader
- Buyer role
- Decision Maker / Budget Holder
- Decision stage
- Which to buy
- Adoption curve
- Early Adopters
- Technology maturity
- Operational Expansion
- Industry
- Information Technology / Software & Services / IT Services / Cloud Services
Our classification, not the publisher's statement. Best suited for, not only for.
Applied Digital said it achieved Ready for Service for Phase 1 of Building 2 at Polaris Forge 1. The company delivered 75 MW of operational AI capacity on schedule, and total live capacity at the Polaris Forge 1 campus reached 175 MW.
The update continued the buildout of Polaris Forge 1, a fully leased AI Factory Campus designed for high-density artificial intelligence and high-performance computing workloads. Applied Digital said that at full build out, Polaris Forge 1 is contracted to deliver 400 MW of critical IT load under long-term lease agreements.
Applied Digital described an AI Factory franchise model that replicates a core design, construction, and operations team across each campus, supported by centralized expertise and dedicated site-level execution teams. The company also cited prior milestones at Polaris Forge 1, including on-time completion of the first 100 MW building.
Wes Cummins, Chairman and Chief Executive Officer of Applied Digital, said, “Delivering this phase on time underscores the strength of our execution model.” He added, “Polaris Forge 1 continues to demonstrate the depth of our team and the discipline it takes to bring critical AI infrastructure capacity online for our customers.” Applied Digital said Polaris Forge 1 is located in Ellendale, North Dakota, where it has operated since 2021.
Press release, provided by Globe Newswire on behalf of Applied Digital. Read the original.